PFE Safety – Key Interlocks

As mentioned in previous posts, there is a high amount of voltage and current on our undersea cables which is supplied by our High Voltage Power Feed Equipment (HVPFE). Due to this high voltage and current generated by an HVPFE, it is critically important that safety procedures be followed at all times when working on this type of equipment.

One important feature built into our PFEs that helps to ensure that proper procedures are followed, and to protect workers when working inside is the HVPFE key interlocks.

These interlocking keys can only be released when certain steps are followed. For example in the above picture, you see key 1 directly above the high voltage switch in our PFE control bay. In order for Key 1 to be captive as shown in the photo, the adjacent converter bay must be powered down and breakers in the off position in order to “release” key 1 from that bay so that you can gain access to the high voltage switch in this bay.

There are multiple sequences like this that are followed when working on a PFE and these sequences will require that certain bays be turned off, certain modules be set to ground, etc, prior to continuing. It literally forces the technicians to put the PFE and the PFE module to be worked on into a “safe” state prior to commencing work.

No comments so far

GPS Time Source

This is a photo of the 3100 and our NTP server which are both located in Sydney.

As discussed in an earlier entry one of the more important aspects in the network particularly in relation to transmission services is network synchronisation.

PPC-1 has a primary reference clock 3100 (PRC) that provide a highly stable time source and clock signal from which our NTP server and our transmission equipment receive their clocking. The device complies with UTUT G811. What this means in practice that we have a very stable clock (stable to better than 100 ns with respect to Universal Coordinated Time (UTC) when locked to a GPS signal, GPS Holdover Time Error: 8.6 µs per day (0 °C to +50 °C, ±5 °C) when not in sight of a GPS satellite.

In frequency terms, a clock signal at 2.048 Mb/s output frequency is accurate to better than: 1 x 10-12 with a GPS Holdover Stability of : 1 x 10-10 per day (0 °C to +50 °C, ±5 °C). This equipment is made by Symmetricom. It is not unique to PIPE as it used by all of the major carriers to synchronise their networks.

Slaved to this device to this device is our NTP server from where our NMS gets its time stamp network wide. Finally, and probably most importantly, our Cisco transmission equipment (ONS 15454) uses a clock signal from the PRC to time the SDH portion of the network and to propagate network clock signals among the ONS elements.

2 comments – Latest by:
  • Michael van der Koff
    Dear Robert, SDH networks require both sides to be sending AND transmitting at the same rate. This differs from the ...
  • Robert
    Why do you use an accurate time source instead of syncing receiver clocks using the edge of binary transitions or ...

Read all comments

Watching the Network (Part 2)

The SNMPc software comprises 2 parts: the core application and an add-on web portal for more sophisticated graphing and reporting options. We are currently running through the initial deployment and have the core software up and running. The web portal aspects will be added in the next couple of weeks.

The SNMP traps will be the primary reporting and monitoring method for the network but we will also have a backup ‘dry contact’ alarm aggregation solution in the unlikely event that we lose SNMP visibility to any device.

When the deployment is complete we expect to have at least 75 discrete pieces of equipment, spread across 6 international sites.

 

5 comments – Latest by:
  • Alan
    Were open-source monitoring solutions considered? Personally, for most network and device monitoring I use a combination of Nagios and Cacti, with ...
  • Matt Whitlock
    Todd, The SNMP manager is giving us a high-level network view of everything (including plant and back office PCs/phones). For ...

Read all comments

Watching the Network (Part 1)

In addition to the specific transmission platforms from Tyco Telecom and Cisco, we have been busy implementing a dedicated Simple Network Management Protocol (SNMP) monitoring solution. It runs on its own dedicated server with a replicated backup server off-site from the primary.

We are using Castle Rock’s SNMPc v7. This allows us to actively monitor and record the performance of all equipment in the network, including environmental monitoring and individual IP telephones and computers. With a 3rd party converter we are even able to collect alarm data from the power systems in the sites.

2 comments – Latest by:
  • Lars Tjernagel
    Darren, thank you for the very good question!! There is no real indication or detail of where a fault is ...
  • Darren Stephens
    With Network Faults how do you know where the fault lies, for example does it give you within repeater 23 ...

Read all comments

Cisco Transmission Equipment Arrives in Sydney

The Cisco 15454 transmission equipment has arrived at the Sydney Cable Landing Station. Once the equipment has been inspected by Matt Whitlock and Lee Harper, it will be dispatched out to the International PoP sites in San Jose in the US and Tokyo in Japan for installation at the end of the month. The Cisco 15454 equipment will be deployed at the edge of the PIPE International Network and function as a managed demarcation point between PPC-1 and its customers.

1 comment – Latest by:
  • Alan
    What line cards did you get in your 15454's? And also out of curiosity, is your SJC PoP in the ...

Read all comments

Preparing for shaky times

It is an engineering requirement that the PPC-1 Cable Station transmission equipment racks are NEBS zone 4 compliant.

The Telecordia NEBS standard defines the industry standard for seismic testing methods and tolerances. These are applicable for communication equipment racks or cabinets which are likely to be deployed in areas where substantial seismic activity is a possibility.

Following the recommendations defined with the NEBS standard, during rack manufactures’ seismic testing programs the rack or cabinet is typically attached to a test concrete slab, loaded with simulated equipment weight and then subjected to a shake test. At its basic level if the rack falls down or distorts past defined tolerances it simply fails the test. In most cases when this occurs the design of the rack has to be stiffened or its specified carrying weight reduced.

Earthquake simulations are basically a series of changes in velocity and acceleration from one vector to another. NEBS Zone 4 seismic testing replicates earthquake scenarios measured on the Richter Scale of 8.3 in magnitude

This video from Chatsworth Products Inc shows clips from the tests of their Zone 4 rated 19″ wide rack with 6″ deep rails. The rack version tested here is to be installed within the PPC-1 Cable Landing Stations.

No comments so far

Type B1 Training in the Sydney CLS

As a part of the Tyco Telecom turnkey scope, 20 days of training are provided at key points during the project. Back in January, Matt and John attended the ‘Type A’ training in New Jersey. This time it was ‘Type B1′ in the Sydney CLS.

The ‘B’ training (of which there are 3 separate courses of 5 days each) take place in each of the cable stations. These photos were taken during Sydney’s 5-day course. In them you can see Matt and John practising the removal of components from the system. It’s important to understand how/when such work would need to be done as well as following correct procedures (cleaning, ESD, console commands). The course was a success with the guys getting their first ‘hands-on’ taste of managing the PPC-1 network. Training has already been completed in Guam and the Tyco Telecom trainer is currently in Papua New Guinea working with the Telikom staff.

‘Type B2′ training will take place in all stations later in the year, once the cable has been laid. ‘Type B3′ will be conducted only in Sydney as it’s more aimed towards the NOC staff, rather than the station technicians.

3 comments – Latest by:
  • Stevo
    Not bad for a mechanical engineer, JB!
  • Matt Whitlock
    Hi Kim, Thanks for the question. You may find that the information in the 'Technology' section of this site useful. ...

Read all comments

The PPC-1 Camera

It’s interesting to note that all the recent underwater and land footage on the blog was taken by our CEO, Bevan Slattery with this little Olympus μTough.

When we were looking for a camera, we needed something that would survive the wide range of environmental conditions that the PPC-1 team encounter daily and be tough enough to endure the harsh treatment that our technicians dish out. We’ve been through a heap of cameras before and none have stood up to the task for any length of time. We never really intended to use if for anything other than just photos, but we were pleasantly surprised at its versatility – it’s waterproof to a 3m depth and records audio underwater (as you’ll notice from yesterday’s blog).

In Guam the camera operated on and off over 16 hours taking over 1 hour of video footage and 150 photos on a single charge. So far this little gem has been to Japan (our CEO took the video footage inside the cable tanks on the Durable which was posted earlier on the PPC-1 blog), Guam and will soon head to Sydney for PPC-1′s Australian Landing. Oh and it’s been on our CEO’s family holiday to Port Douglas including lots of underwater shots of the Great Barrier Reef ;-) .

As you can tell, we love this camera and this post is our salute to the mighty Olympus μTough. At less than $500 this camera rocks.

3 comments – Latest by:
  • Zoe Hellar
    Olympus PPC-1 Camera Nowadays there is more of a choice of these robust cameras.I want one.
  • Bevan Slattery
    We've already bought another 3 for staff. I've heard Tyco bought another 40 for their guys. I seriously love this ...

Read all comments

Sydney installation continues…

Delivering the containers was a feat of precision driving as only one of the trucks had the required side lifters to unload the containers. One container was put in position; the second truck was then brought alongside and the container moved from one to the other; and then to the ground.

With the Tyco Telecom team on-site to accept the delivery, the installation in Sydney is underway with both containers being unpacked and their inventory checked.

1 comment – Latest by:
  • Wayne
    What fun it would be to unpack. It would be like a big birthday present haha. Keep up this blog, ...

Read all comments