Day 45 - more of the same... 

We were starting to run out of things to show you on the blog - there's a lot of work going on, but nothing that's particularly visible is happening (more visible things should start happening tomorrow). The sparkies are lugging and terminating large power cables, the floor section that's already done is having it's cut tiles put in place, the A/C units are positioned on their stands, the fibre guys have had a look at installing their fibre termination racks, and various other significant, but not hugely visible things have been happening.

...but, we took a stroll up to the roof to see how the air conditioning work up there was going. Pictured are the stage 1 outdoor units (the units for the UPS room are just to the left of these, out of the shot).

The pipework on the roof is well underway, and it's extended most of the way down to the ceiling slab of our tenancy.


[ 1 comment ] ( 47 views ) permalink related link ( 3 / 107 )
Day 44 - flooring started 

the flooring contractors have started the flooring at the far end of the room earlier than we'd expected, and are scheduled to continue through the rest of the room starting tomorrow.



The air conditioning contractors have started lifting the A/C units into place - delayed slightly by the late arrival of the lifting equipment.

The power cabling is coming along nicely, with most of the UPS cabling now in place and being terminated.

[ 2 comments ] ( 198 views ) permalink related link ( 3.2 / 121 )
Day 40 - the floor arrives 

Another busy day today - more Unistrut floor supports for the underfloor power and air conditioning pipework were installed.

The new fire cabling tray was installed to allow us to replace and neaten the existing building fire cabling that feeds the complex. That will take away a good portion of the ugly cabling that was previously in the roof cavity.

Core boring for the air conditioning pipework continued today.

The copper tubing itself and the associated insulation for the air conditioning arrived.

Power cabling continued, and will continue for most of next week. It's a big job - every cable needs to be run through the traywork, neatly tied down, and eventually terminated and tested.

Our webcam broke today - during the building work the temporary phone extension cable we're using suffered some damage. It was fixed mid afternoon and all is good again.

Most significantly the flooring started to arrive today - there's 3 truckloads of flooring going into this section of the facility (the picture shows some of the tiles located in the end section of the room).


[ 2 comments ] ( 145 views ) permalink related link ( 2.9 / 112 )
Day 39 - let there be light... 

Today the datacentre lights were livened up - they're on a temporary power supply for now. It was important to get these operating so that the contractors working in that area can see what they're doing.



In the photo we've got one of the guys from Surepower making the cable penetrations in the battery circuit breaker enclosures. These will be installed shortly.

Down the back is one of the fire contractors getting prepared to start their work - they have to relocate the existing building fire cabling (it was previously draped across the roof cavity above the false ceiling that was there), and they have to install the gas suppression system.

The air conditioning condensers were craned up to the roof this morning at around 6am and the A/C contractors have been working on those.

The first power cable inside the power & UPS room was run today, as can be seen in the photo below. These are the UPS input cables in the supply switchboard - 4 cables per UPS (3 phases and neutral). This is one of two cable chambers - the other two stage-1 UPS's connect through the other chamber.



The flooring didn't arrive today as we expected - the deliveries are apparently happening tomorrow and Saturday (they tell us it's being delivered in 3 truckloads).

The actual flooring should start going down towards the end of next week - it's being delayed so the under-floor trays, air conditioning positioning and pipework, and a couple of above floor activities can be completed first.
[ add comment ] permalink related link ( 3 / 104 )
Day 38 - more electrical work 

Today was another busy day.

The air conditioning condensers were removed from their crates and prepared for the lift to the roof tomorrow morning.

The remaining UPS's for stage-1 were positioned and bolted down today, and the batteries mostly loaded into the battery cabinets (pictured here still in the shipping container - there's a dozen more of these containers)



The sparkies pretty much finished off the installation of the lights, ready for them to be powered up tomorrow.

The flooring has been delayed slightly and is expected on-site tomorrow.

Builders bricked up one of the remaining doors today, leaving only the entry door and the necessary fire exits.
[ add comment ] permalink related link ( 3 / 102 )