Another busy day today - more Unistrut floor supports for the underfloor power and air conditioning pipework were installed.
The new fire cabling tray was installed to allow us to replace and neaten the existing building fire cabling that feeds the complex. That will take away a good portion of the ugly cabling that was previously in the roof cavity.
Core boring for the air conditioning pipework continued today.
The copper tubing itself and the associated insulation for the air conditioning arrived.
Power cabling continued, and will continue for most of next week. It's a big job - every cable needs to be run through the traywork, neatly tied down, and eventually terminated and tested.
Our webcam broke today - during the building work the temporary phone extension cable we're using suffered some damage. It was fixed mid afternoon and all is good again.
Most significantly the flooring started to arrive today - there's 3 truckloads of flooring going into this section of the facility (the picture shows some of the tiles located in the end section of the room).

The new fire cabling tray was installed to allow us to replace and neaten the existing building fire cabling that feeds the complex. That will take away a good portion of the ugly cabling that was previously in the roof cavity.
Core boring for the air conditioning pipework continued today.
The copper tubing itself and the associated insulation for the air conditioning arrived.
Power cabling continued, and will continue for most of next week. It's a big job - every cable needs to be run through the traywork, neatly tied down, and eventually terminated and tested.
Our webcam broke today - during the building work the temporary phone extension cable we're using suffered some damage. It was fixed mid afternoon and all is good again.
Most significantly the flooring started to arrive today - there's 3 truckloads of flooring going into this section of the facility (the picture shows some of the tiles located in the end section of the room).








Calendar



