Day 19 

You can't tell too much by the photo but here are our builders finishing the final preparation for painting. The walls will set over the long weekend, and painting will commence on Tuesday.


[ add comment ] permalink related link ( 3.4 / 149 )
Day 18 

Excuse the photos below, DC3 was today a dust storm. The builders continued to set the walls, plastering over the joints and corners, then sanding back the walls in preparation for a second base coat.


Looking through into the foyer area


Looking down the Western internal wall of DC3
[ add comment ] permalink related link ( 3.2 / 154 )
Day 17 - Prep and Paint 

The wall sheeting was completed first thing this morning.

Then plasterers came along to start prepping areas of the walls and ceilings.

Plasters moved out to make way for painters this afternoon, and we now have a data centre with walls and a seal coat.

Unfortunatley no pics today as someone forgot to put energiser batteries into the camera - can't wait to have the web cam up and running.
[ add comment ] permalink related link ( 3.3 / 175 )
Day 16 

Now it's starting to look a bit more like a Data Centre. The builders had a busy day getting the sheeting about 80% complete. Our UPS and Switch Board room is completely closed in, and the entry foyer is boxed and awaiting the return of the builders tomorrow morning. We expect all sheeting to be completed tomorrow so that walls and ceiling can be prepped for painting.

Our web cam is clicking away, we’re just waiting on the DSL so that we can install it for real-time Big Brother cam action from DC3.


[ 2 comments ] ( 91 views ) permalink related link ( 3.1 / 149 )
Day 15 - Construction well under way 

It's day 15 and the builders are well underway with the construction of the internal walls. They're a little more advanced that this photo suggests - over the next couple of days the Fyrchek sheeting goes up, and the perimeter sheeting is completed. Once that's done the whole shebang gets a coat of paint and the equipment starts to arrive.

The Fyrchek sheeting will give us a 120/120 fire rating between the electrical room and the customer equipment room.


[ add comment ] permalink related link ( 3 / 143 )