It's day 11 and the first 4 UPS's are in storage awaiting delivery and installation (the unit pictured is still screwed down to the pallet).
The initial installation will have 4 of these UPS's - two on the 'A' side, and two on the 'B' side. As the site grows, more of these units will be brought online for a total of 8 units.
Construction of the switch room, which will house the switchboards and UPS's commenced today with the framing all but complete.
The webcam went in today - we're just waiting on the DSL to be installed so we can get it online. Until that's done we'll look at bringing images back periodically on a flash drive.

The initial installation will have 4 of these UPS's - two on the 'A' side, and two on the 'B' side. As the site grows, more of these units will be brought online for a total of 8 units.
Construction of the switch room, which will house the switchboards and UPS's commenced today with the framing all but complete.
The webcam went in today - we're just waiting on the DSL to be installed so we can get it online. Until that's done we'll look at bringing images back periodically on a flash drive.